NEWS

CERC redevelopment timetable

Marsh Farm Community Development Trust is undertaking a major refurbishment project. The Community Enterprise Resource Centre (CERC) is being transformed into a new community building bringing longer term benefits to the residents of Marsh Farm. Work is now well underway with the building on course for opening in January 2011. For a timeline of building works see below:

June 2010: The second stage of Demolition begins.

September 2010: The second stage of Construction begins.

January 2011: The NEW Community Enterprise Resource Centre will be completed by January 2011.

main news image

Recent POSTS

A FUN DAY FOR ALL AT THE FESTIVAL

Fun at the festival

CERC REDEVELOPMENT TIMETABLE

Marsh Farm Community Development Trust is undertaking a major refurbishment project. The Community Enterprise Resource Centre (CERC) is being transformed into a new community building bringing longer term benefits to ...

LATEST NEWS ON NEW CERC FROM VOLKERFITZPATRICK

The new CERC building is starting to take shape. The demolition of the old building will reveal over the next few weeks the new structure that is being constructed behind. ...

BUSINESS AS USUAL

The demolition of the old building may be underway but it is still business as usual for MFCDT.

See full Archive